Energy Sector

173 Power Stations
199.00 Installed Capicity
142.75 Generation Summer-MW
87.50 Generation Winter-MW
Name of Facility Commisioned District Capacity (MW) Summer Generation Winter Generation Status
Hydel Station Gharbuchung 1991 Ghanche 0.22 0.16 0.00 Operational
Hydel Station Pion 1998 Ghanche 1.00 0.50 0.13 Operational
Hydel Station Haassanabad Ghanche 2012 Ghanche 0.70 0.40 0.30 Operational
0.5 MW Hydro Power Station Chowar Ghanche. 2017 Ghanche 0.50 0.35 0.00 Operational
1.5 MW Hydro Power Station Saith Saltoro Ghanche 2021 Ghanche 1.50 1.20 1.00 Operational
0.5 MW Hydro Power Station Karis Ghanche 2021 Ghanche 0.50 0.40 0.30 Operational
0.3 KW Hydro Power Project Kandy Hushay 2022 Ghanche 0.30 0.25 0.20 Operational
1 MW Hydro Power Proejct Balygond Gahnche Stage-I 2022 Ghanche 2.00 1.80 1.30 Operational
Hydel Station Harchu 1992 Astore 0.40 0.37 0.30 Operational
Hydel Station Derlay 1994 Astore 0.20 0.15 0.10 Operational
Hydel Station Rattu 1987 Astore 0.16 0.14 0.08 Operational
Hydel Station Lause 1990 Astore 1.00 0.85 0.70 Operational
Hydel Station Perishing 2010 Astore 2.00 1.50 1.30 Operational
Hydel Station Mir Malik 2017 Astore 0.40 0.12 0.07 Operational
Hydel Station Perishing Ph-III 2020 Astore 1.50 1.40 0.80 Operational